|
|
|
|
|
Contents
2.1.1
Monitoring Requirements and Equipment
2.1.2
Monitoring Schedule for the Reporting Month
2.1.3
Results and Observations
2.2.1
Monitoring Requirements and Equipment
2.2.2
Monitoring Schedule for the Reporting Month
2.2.3
Results and Observations
2.5.1
Preserved Plant Species of Conservation Importance
2.5.2
Transplanted Plant Species of Conservation Importance
2.7.2
Monitoring Schedule for the Reporting Month
2.7.3
Results and Observations
2.10 LANDSCAPE AND VISUAL
MONITORING
2.11 IMPLEMENTATION STATUS OF
ENVIRONMENTAL MITIGATION MEASURES
2.12 SUMMARY OF COMPLAINTS, NOTIFICATION OF SUMMONS AND
SUCCESSFUL PROSECUTIONS
ANNEX b
Environmental Mitigation Implementation Schedule
ANNEX c
Status of Submissions and Implementation Status of Mitigation Measures
under EP
ANNEX d
Status of Statutory Environmental Requiremens
ANNEX e1
Calibration Certificates for Air Quality
ANNEX e2
Monitoring Schedule for Air Quality
ANNEX e3
Monitoring Results for Air Quality
ANNEX e4
Event and Action Plan for Air Quality
ANNEX f1
Calibration Certificates for Noise
ANNEX f2
Monitoring Schedule for Noise
ANNEX f3
Monitoring Results for Noise
ANNEX f4
Event and Action Plan for Noise
ANNEX g
Compensation Woodland Monitoring
ANNEX h
Preserved/Transplanted Plant Species of Conservation Importance
Monitoring
ANNEX h1
Preserved Plant Species of Conservation Importance
ANNEX h2
Transplanted Plant Species of Conservation Importance
ANNEX I
Eco-shoreline Monitoring
ANNEX J3
event and action plan
ANNEX K
Landscape and Visual Monitoring
ANNEX K1
Examples of Landscape and Visual Mitigation Measures
ANNEX K2
Event and Action Plan for Landscape and Visual Mitigation Measures
ANNEX M Monitoring
Schedule for the Next Reporting Period
List of
Tables
Table 1.1 Contact Information of Key
Personnel
Table 1.2 Major Activities in the
Reporting Period
Table 1.3 Summary of Status for the
Environmental Aspects under the Updated EM&A Manual
Table 2.1 Action and Limit Levels
for 1-hour TSP
Table 2.2 Air Quality Monitoring
Details
Table 2.3 Summary of 1-hour TSP
Monitoring Results in the Reporting Period
Table 2.4 Action and Limit Levels
for Construction Noise
Table 2.5 Noise Monitoring Details
Table 2.6 Summary of Construction
Noise Monitoring Results in the Reporting Period
Table 2.7 Summary of Qualitative
Walk-through Surveys
Table 2.8 Results of Sedimentation
Rate Monitoring
Table 2.9 Key Observations
Identified during the Site Inspection in this Reporting Month
Table 2.10 Quantities of Different Waste
Generated and Imported Fill Materials 20
Table 2.11 Implementation Status of
Landscape and Visual Mitigation Measures
LIST OF FIGURES |
|
MARINE ECOLOGICAL MONITORING (INTERTIDAL SOFT-SHORE HABITATS) |
|
Acronyms and abreviations
Acronyms |
Description |
C&D |
Construction and Demolition |
CAP |
Contamination Assessment Plan |
CEDD |
Civil Engineering and Development Department |
CWD |
Chinese White Dolphin |
DCM |
Deep Cement Mixing |
DO |
Dissolved Oxygen |
EIA |
Environmental Impact Assessment |
EIAO |
Environmental Impact Assessment Ordinance |
EIS |
Ecologically Important Stream |
EM&A |
Environmental Monitoring and Audit |
EP |
Environmental Permit |
EPD |
Environmental Protection Department |
ER |
Engineer's Representative |
ERM |
ERM-Hong Kong, Limited |
ET |
Environmental Team |
HVS |
High Volume Sampler |
IEC |
Independent Environmental Checker |
PDA |
Planned Development Area |
PME |
Powered Mechanical Equipment |
QPME |
Quality Powered Mechanical Equipment |
RAP |
Remediation Action Plan |
RR |
Remediation Report |
RTTM |
Real Time Tracking and Monitoring |
SS |
Suspended Solid |
TCB |
Tung Chung Bay |
TCE |
Tung Chung East |
TCNTE |
Tung Chung New Town Extension |
TCW |
Tung Chung West |
The Project |
Tung Chung New Town Extension (East) |
THW |
Tai Ho Wan |
TSP |
Total Suspended Particulate |
TUE |
Tung Chung Line Extension |
Updated EM&A Manual |
Updated Environmental Monitoring and Audit Manual for Tung Chung New Town Extension prepared by ERM under Agreement No. CE 60/2017 (EP) and deposited to EPD under Environmental Permit No. EP-519/2016 |
Tung Chung New Town Extension
(TCNTE) is one of the major initiatives under the Government's multi-pronged approach
to increase land supply to meet Hong Kong's medium- to long-term needs for
housing, economic and social developments. The Environmental Impact
Assessment (EIA) Report for TCNTE (Register No. AEIAR-196/2016) was approved on
8 April 2016 and the Environmental Permit (EP) No. EP-519/2016, covering the
construction and operation of TCNTE, was granted on 9 August 2016. The
EIA Report and EP cover both Tung Chung East (TCE) and Tung Chung West
(TCW). ERM-Hong Kong, Limited (ERM) is commissioned to undertake the role
of Environmental Team (ET) for the construction and operation of TCE Project
(“the Project”) in accordance with the requirements specified in the EP,
Updated Environmental Monitoring and Audit (EM&A) Manual, EIA Report of the
TCNTE project and other relevant statutory requirements.
The construction of the Contract
No. NL/2017/03 - Tung Chung New Town Extension –
Reclamation and Advance Works (“Contract 1”) at TCE commenced on 9 July
2018.
The construction of the Contract
No. NL/2020/02 - Tung Chung New Town Extension – Salt Water
Supply System (“Contract 2”) at TCE commenced on 4 September 2021.
The construction of the Contract No.
NL/2020/03 - Tung Chung New Town Extension – Major Infrastructure Works in Tung
Chung East (“Contract 3”) at TCE commenced on 5 November 2021.
The construction of the Contract
No. NL/2020/07 - Tung Chung New Town Extension – Tai Ho Interchange (“Contract
7”) at TCE commenced on 15 March 2022.
The temporary works area in Area
113 has been used by MTRC since 9 November 2024 under the Works Contract 1202 –
Tung Chung East Station and Associated Enabling Works for Track Diversions of
Tung Chung Line Extension (TUE) under the Environmental Permit (EP-614/2022).
The corresponding environmental monitoring, site inspection, environmental
complaint handling and EM&A reporting in the above-mentioned works area
will be covered by EM&A programme of TUE and
carried out by existing ET and IEC of TUE.
This is the Monthly EM&A report
presenting the EM&A works carried out during the period from 1 to 31
December 2024 for the TCE Project in accordance with the Updated EM&A
Manual.
A summary of monitoring and audit
activities conducted in the reporting period is listed below:
Air Quality
Monitoring
6 sessions
Noise
Monitoring
6 sessions
Compensation
Woodland Monitoring 1
session
Preserved Plant Species
Monitoring 1
session
Transplanted Plant Species Monitoring
1 session
Soft
Shore Ecological
Monitoring
1 session
Environmental
Site Inspection
·
Contract
2
5 sessions
·
Contract
3
4 sessions
·
Contract
7
5 sessions
Environmental
Management Meeting
·
Contract
2
1 session
·
Contract
3
1 session
·
Contract
7
1 session
Environmental auditing works,
including weekly site inspections of construction works conducted by the ET,
audit of implementation of Complaint Management Plan, Eco-shoreline
Implementation Plan, Detailed Preservation and/or Translocation of Plant Species
of Conservation Importance, Detailed Compensatory Woodland Planting Plan and Waste Management Plan
were conducted in the reporting period. Based on the audit results and
the observation for the reporting period, environmental pollution control and
mitigation measures for the Project were properly implemented.
No exceedance of Action and Limit
Levels was recorded for construction air quality monitoring in the reporting
period.
No exceedance of Action/Limit
Levels was recorded for construction noise monitoring in the reporting
period.
Water quality monitoring was
suspended in the reporting period.
The construction of vertical
eco-shoreline, mangrove eco-shoreline and rocky eco-shoreline has been
substantially completed. No
eco-shoreline monitoring was scheduled during the reporting period.
Based on the post-construction
monitoring conducted during the reporting period, there was no evidence showing
any significant difference in intertidal communities when compared against the
data obtained during baseline monitoring. The ET will continue to observe
the change in density or the distribution pattern of horseshoe crab, seagrass
and intertidal soft shore communities taking into
account natural fluctuation in respect of the occurrence and
distribution pattern.
There was no
notification of summons or prosecution recorded in the reporting period.
No environmental complaint was received in the reporting
period. The environmental complaint handling and EM&A reporting in
the temporary works area in Area 113 used by MTRC will be covered by EM&A programme of TUE and carried out by existing ET and IEC of
TUE.
There
was no reporting change in the reporting period.
Potential environmental impacts
arising from the upcoming construction activities in the next reporting period
of January 2025 are mainly associated with dust emission, noise from plant
operation during normal working hours and restricted hours, handling and
storage of C&D materials generated from construction activities, efficiency
of wastewater and drainage management and tree protection. The ET will
keep track on the construction works to confirm compliance of environmental
requirements and the proper implementation of all necessary mitigation
measures. The ET will also recommend to the Contractor about the
environmental toolbox topics on the abovementioned key issues for the coming
month.
Tung Chung New Town Extension
(TCNTE) is one of the major initiatives under the Government's multi-pronged
approach to increase land supply to meet Hong Kong's medium- to long-term needs
for housing, economic and social developments. The Environmental Impact
Assessment (EIA) Report for TCNTE (Register No. AEIAR-196/2016) was approved on
8 April 2016 and the Environmental Permit (EP) No. EP-519/2016, covering the
construction and operation of TCNTE, was granted on 9 August 2016. The EIA
Report and EP cover both Tung Chung East (TCE) and Tung Chung West (TCW).
ERM-Hong Kong, Limited (ERM) is
commissioned to undertake the role of Environmental Team (ET) for the
construction and operation of TCE Project (“the Project”) in accordance with
the requirements specified in the EP, Updated Environmental Monitoring and Audit
(EM&A) Manual ([1]),
EIA Report of the TCNTE project ([2])
and other relevant statutory requirements.
The TCNTE
comprises the following elements:
(a) TCE
Project
1. Reclamation of the
seabed by a non-dredged method at TCE to form a total of about 130 hectares of land;
2. Construction of about 4.9
kilometers of seawalls, with an eco-shoreline, three
drainage box culvert outfalls, three circulation drains and a seawater intake
at TCE;
3. Provision of
infrastructure for Tung Chung Area 58, including construction of a single
two-lane road with a footpath and the associated utility works;
4. Construction of
proposed open space;
5. Construction of roads,
footpaths, cycle tracks and the associated junction / road improvement works;
6. Engineering
infrastructure works covering drainage, sewerage, waterworks (including a fresh water service reservoir, a salt water service
reservoir and a salt water pumping station), common utility tunnels and
landscaping works; and
7. Implementation of
environmental mitigation measures and environmental monitoring and audit
programme for the works.
(b) TCW
Project
1. Site formation works at TCW;
2. Construction of proposed
open space;
3. Construction of the River
Park including a visitor centre at TCW; and
4. Construction of sustainable urban drainage
systems at TCW.
The locations of Contracts 1, 2,
3 and 7 are shown in Figure
1.1 to 1.4. The construction and the reclamation related marine
works of Contract 1 commenced on 9 and 13 July 2018, respectively. The
construction of Contracts 2, 3 and 7 commenced on 4 September 2021, 5 November
2021 and 15 March 2022, respectively.
This is the Monthly EM&A
Report for the TCE Project which summarises the key
findings of the EM&A programme during the
reporting period from 1 to 31 December 2024 for the construction works.
The
organization structure of the Project is shown in Annex A. The key
personnel contact names and contact details are summarized in Table 1.1
below.
Table 1.1 Contact Information of Key Personnel
Party |
Position |
Name |
Telephone |
Environmental Team (ET) (ERM-Hong Kong, Limited) |
ET Leader |
Kelvin So |
3894 9504 |
Deputy ET Leader |
Raymond Chow |
2271 3281 |
|
Independent Environmental Checker (IEC) (Binnies Hong Kong Limited) |
IEC |
Manuel Chua |
3894 9807 |
Deputy IEC |
Edward Lau |
3894 9695 |
|
Contract No. NL/2017/03 - Tung Chung New Town Extension – Reclamation and Advance Works (Contract 1) |
|||
Civil Engineering and Development Department |
Marine Conservation Officer |
Wo King Tai |
3894 9707 |
Engineer’s Representative (ER) (AECOM Asia Company Limited)
|
Principal Resident Engineer |
Frankie Fan |
3894 9603 |
Chief Resident Engineer |
Chris Cheung |
3894 9604 |
|
Resident Engineer |
Victor Chan |
3894 9666 |
|
Inspector of Works |
Clement Fan |
3894 9798 |
|
Contractor (Build King – SCT Joint Venture)
|
Site Agent |
David Wong |
9653 8635 |
Civil Division Head |
Marco Chan |
9257 7033 |
|
Environmental Officer |
Issac Wong |
9873 8968 |
|
24-hour Complaint Hotline |
- |
5976 1853 |
|
Contract No. NL/2020/02 - Tung Chung New Town Extension – Salt Water Supply System (Contract 2) |
|||
Civil Engineering and Development Department |
Senior Engineer |
Patrick C Y Yeung |
2231 4435 |
Electrical & Mechanical Engineer |
Samson K L Yip |
2231 4460 |
|
Engineer’s Representative (ER) (AECOM Asia Company Limited)
|
Principal Resident Engineer |
Frankie Fan |
3894 9603 |
Senior Resident Engineer |
Sunny Ng |
3894 9605 |
|
Senior Resident Engineer |
Vincent Leung |
3894 9645 |
|
Resident Engineer |
Amen Fung |
3894 9676 |
|
Senior Inspector of Works |
Lai Kwok Wai |
3894 9731 |
|
Contractor (China Geo-Engineering Corporation)
|
Construction Manager |
Ambrose Kwong |
6198 7787 |
Site Agent |
Edward Mok |
6498 4306 |
|
Construction Team Leader |
C K Chung |
5401 5720 |
|
Environmental Officer |
Fung Ka Bao |
9120 1489 |
|
24-hour Complaint Hotline |
- |
5976 1853 |
|
Contract No. NL/2020/03 - Tung Chung New Town Extension – Major Infrastructure Works in Tung Chung East (Contract 3) |
|||
Civil Engineering and Development Department
|
Senior Engineer |
Eddie W C Lam |
2231 4445 |
Senior Engineer |
Phoebe Tang |
2231 4423 |
|
Engineer |
Timothy H M Chan |
2231 4473 |
|
Engineer |
Colin K C Wong |
2231 4417 |
|
Engineer |
Wing Chen |
3894 9704 |
|
Engineer’s Representative (ER) (AECOM Asia Company Limited)
|
Principal Resident Engineer |
Frankie Fan |
3894 9603 |
Chief Resident Engineer |
Gloria Tang |
3894 9639 |
|
Senior Resident Engineer |
Winston Wong |
3894 9650 |
|
Resident Engineer |
Alvis Li |
3894 9558 |
|
Resident Engineer |
Anson Yip |
3894 9559 |
|
Senior Inspector of Works |
Douglas Ng |
3894 9737 |
|
Contractor (Build King Civil Engineering Limited)
|
Construction Manager |
Cheung Siu Lun |
2272 3680 |
Site Agent |
Aldous Lo |
9225 0368 |
|
Deputy Site Agent |
Keith Chau |
9646 8283 |
|
Construction Team Leader |
Kwong Po Hang |
9283 6844 |
|
Environmental Officer |
Tim Lin |
6390 0018 |
|
24-hour Complaint Hotline |
- |
5976 1853 |
|
Contract No. NL/2020/07 - Tung Chung New Town Extension – Tai Ho Interchange (Contract 7) |
|||
Civil Engineering and Development Department |
Senior Engineer |
Phoebe Tang |
2231 4423 |
Engineer |
S H Leung |
2231 4449 |
|
Engineer’s Representative (ER) (AECOM Asia Company Limited) |
Principal Resident Engineer |
Frankie Fan |
3894 9603 |
Senior Resident Engineer |
Kelvin Kwan |
3894 9641 |
|
Senior Resident Engineer |
Brian Li |
3894 9556 |
|
Resident Engineer |
Kingsley Ho |
3894 9552 |
|
Resident Engineer |
Jessie Tang |
3894 9678 |
|
Senior Inspector of Works |
C K Liu |
3894 9733 |
|
Contractor (Build King Civil Engineering Limited) |
Site Agent |
Hon Yee |
9090 3109 |
Deputy Site Agent |
Vincent Kwan |
9833 1313 |
|
Construction Team Leader |
Vincent Lo |
9883 9229 |
|
Environmental Officer |
Nash Wong |
9810 1946 |
|
24-hour Complaint Hotline |
- |
5976 1853 |
As informed by the
Contractor, details of the major works carried out in this reporting period are
listed below:
Table 1.2 Major Activities in the Reporting Period
Activities |
Key Issues |
Key Mitigation Measures |
Contract No. NL/2017/03 - Tung Chung New Town Extension – Reclamation and Advance Works (Contract 1) |
||
Land-based Works |
||
· Removal of siltation at IORC
|
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management · Potential surface runoff · Noise from plant operation during normal working hours or restricted hours · Dust emission during storage and transfer of sand/ sorted public fill |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management · Strictly follow requirement under CNP for the use of PMEs and works within restricted period · Use of acoustic mat and other noise mitigation measures when necessary · Regular maintenance of engines and mechanical equipment |
Contract No. NL/2020/02 - Tung Chung New Town Extension – Salt Water Supply System (Contract 2) |
||
Land-based Works |
||
· Construction of pumping station at Portion 6 · Construction of Intake Culvert at Portion 6 · Construction of service reservoir and TMF mainlaying at Portion 3 · Construction of HDD works at Portion 3 · Watermain laying works at Portion 3 along Man Tung Road, Coastal Skyline and Waterfront Road · Construction of L3 Road at Portion 5
|
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management · Tree protection |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management · Retain and protect all existing trees and vegetation within the study area which are not directly affected by the works |
Contract No. NL/2020/03 - Tung Chung New Town Extension – Major Infrastructure Works in Tung Chung East (Contract 3) |
||
Land-based Works |
||
· Excavation and ELS works at Portion 104 · Excavation and ELS works at CUT no.1, 2, 3, 4 and supporting building · Construction works for CUT no. 1 and 3 structure · Back-filling works for CUT 2 · Construction works and furniture installation of PM office at WA9 · Construction works of Contractor office at WA6 · Drainage, Sewerage and watermain works at Road L5, L7, L8, L9, D4 and D5 and Portion 16 · DCS works at Road L5, D4 and L7. · Pipe laying works for twin rising mains/ watermain laying at Man Tung Road · Preparation and pipe jacking works at Ying Tung Road · Pipe jacking works at Yi Tung Road · Backfilling works for noise barrier at Portion 11 · Road and drainage works in Road P1 · Road works in Road L3 and L4 · Road widening works at Ying Hei Road · ELS for SIBC construction · Construction for BC3 at Portion 22B Pipe pile installation at underpass D1 |
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management
|
Contract No. NL/2020/07 - Tung Chung New Town Extension – Tai Ho Interchange (Contract 7) |
||
Land-based Works |
||
· Open cut excavation, backfilling and pipe laying for rising main and watermain at Portion 146-1 to 146-5 · Pak Mong Bridge insitu construction of abutment, diaphragm and cable trough · Trench excavation and pipe laying works at Portions 32 (Sham Shui Kok Drive) · Trench excavation and pipe laying works at Portion 32 (Access Road adjacent to MTRC Siu Ho Wan Depot) · Establishment of pipe jacking works at Portion 33 · Horizontal grouting at Receiving pit at Portion 32 · RC construction of Retaining Wall FR1 at Portion 31 · Pak Mong Subway Extension Phase 2 - Demolition of existing Subway and Sheetpiling for ELS · Formwork and rebar fixing for Bridge A1 and A2 · RC construction for A1a, A1b, A2a, A2b Abutment · RC for RW-R2 at Portion 146-4 · RC construction at RW-R7 at Portion 31 · RC works at Wall E · Mini-piles at Wall D · Pile cap construction for Bridge C at Portion 146-12 · Excavation and RC works for Box Structure C1at Portion 146-11 · Pipe connection to BC6 from Portion 147 · U channel and chain link fence construction at Portion 147-1 and 147-2 · Sign gantry ELS, RC works, crossroad ducts, temporary lighting arrangement and removal of central divider along NLH fast lane · Drainages works at 146-4, 146-6 and 146-7 · Site clearance and tidiness
|
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management · Tree protection |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management · Retain and protect all existing trees and vegetation within the study area which are not directly affected by the works |
The environmental mitigation implementation
schedule is presented in Annex
B.
The status for all
environmental aspects is presented in Table 1.3. The EM&A
requirements remained unchanged during the reporting period.
Table 1.3 Summary of Status for the Environmental Aspects
under the Updated EM&A Manual
Parameters |
Status |
|
Air Quality |
||
Baseline Monitoring |
The results of baseline air quality monitoring for TCE were reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.4 |
|
Impact Monitoring |
On-going for TCE, monitoring conducted three times every six days |
|
Noise |
|
|
Baseline Monitoring |
The results of baseline noise monitoring for TCE were reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.4 |
|
Impact Monitoring |
On-going for TCE, monitoring conducted once per week |
|
Impact Monitoring for Road Traffic Noise during Operational Phase |
To be conducted during operational phase |
|
Fixed Noise Commissioning Test |
To be implemented by the Contractor before operation of TCNTE |
|
Water Quality |
|
|
Baseline Monitoring |
The results of baseline water quality monitoring for TCE were reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.4 |
|
Impact Monitoring |
Suspended for TCE with approval from EPD |
|
Waste Management |
|
|
Waste Monitoring |
On-going |
|
Land Contamination |
|
|
Contamination Assessment Plan (CAP), Remediation Action Plan (RAP) and Remediation Report (RR) |
To be conducted under TCW. Refer to the EM&A Reports of TCW. |
|
Ecology |
|
|
Monitoring for Compensation Woodland
|
Compensation Woodland Planting was completed on 30 September 2022 On-going, monitoring conducted quarterly. Quarterly post-planting monitoring report was submitted to EPD on 10 December 2024. |
|
Monitoring for Emergent Plant inside the future River Park |
To be conducted under TCW. Refer to the EM&A Reports of TCW. |
|
Monitoring for Translocated Amphibians of Conservation Importance |
To be conducted under TCW. Refer to the EM&A Reports of TCW. |
|
Monitoring for Preserved/Transplanted Plant Species of Conservation Importance
|
On-going, for preserved plant species, monitoring conducted once per month; for transplanted plant species, replacement planting was carried out on 28 April 2023 and 19 September 2023. Monitoring conducted once per month for the first year, and quarterly for the second year. |
|
Monitoring for Tung Chung Stream EIS and Wong Lung Hang EIS
|
To be conducted under TCW. Refer to the EM&A Reports of TCW. Monitoring for Wong Lung Hang was not required and the proposal was accepted by EPD on 2 September 2021 |
|
Eco-shoreline Monitoring |
The dry season monitoring between December 2023 and February 2024 was completed. Wet season monitoring between May 2024 and August 2024 was completed. The 2nd Progress report of the eco-shoreline monitoring was submitted to AFCD and EPD on 23 December 2024. |
|
Tung Chung Bay and Tai Ho Wan Baseline Monitoring |
The results of baseline soft shore ecological monitoring at Tung Chung Bay and Tai Ho Wan were reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.4 |
|
Tung Chung Bay and Tai Ho Wan Impact Monitoring |
Completed |
|
Tung Chung Bay and Tai Ho Wan Post-construction Monitoring |
On-going for TCE, monitoring conducted quarterly |
|
Landscape and Visual |
|
|
Baseline Monitoring |
The results of baseline landscape and visual monitoring were reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.4 |
|
Impact Monitoring |
On-going |
|
Site Environmental Audit |
|
|
Regular Site Inspection |
On-going |
|
Dolphin Watching Plan implementation measures |
Completed |
|
Works Vessel Travel Route Plan implementation measures |
Completed |
|
Silt Curtain Deployment Plan implementation measures |
All silt curtain was removed in accordance with the Silt Curtain Deployment Plan and after obtaining the acceptance from EPD |
|
Spill Response Plan implementation measures |
Completed |
|
Detailed Preservation and/or Translocation Plan for Plant Species of Conservation Importance implementation measures |
Under implementation by the Contractor of Contract 2 |
|
Detailed Compensatory Woodland Planting Plan implementation measures |
Under implementation by the Contractor of Contract 2 |
|
Waste Management Plan implementation measures |
Under implementation by the Contractor of Contract 1, 2, 3 and 7 |
|
Complaint Hotline and Email Channel |
Under implementation by the Contractor of Contract 1, 2, 3 and 7 |
|
Environmental Log Book |
On-going |
|
Taking into account
the construction works, impact monitoring of air quality, noise and waste
management were carried out in the reporting period. The monitoring
schedule of air quality and noise are provided in Annex E2 and Annex F2 respectively.
The EM&A programme also involved environmental site inspections and
related auditing conducted by the ET for checking the implementation of the
required environmental mitigation measures recommended in the approved EIA
Report and relevant EP submissions, including Complaint Management Plan,
Eco-shoreline Implementation Plan, Detailed Preservation and/or Translocation
Plan for Plant Species of Conservation Importance, Detailed Compensatory
Woodland Planting Plan and Waste Management Plan.
To promote the
environmental awareness and enhance the environmental performance of the
contractors, environmental trainings and regular environmental management
meetings were conducted during the reporting period, which are summarized as
below:
•
Three (3) environmental management committee meetings were held among the
relevant contractors, ER, ET, IEC and CEDD on 18, 17, 10 December 2024 for
Contracts 2, 3 and 7;
•
Environmental toolbox trainings on handling and storage of
chemicals/chemical waste and handling of chemical spillage, stockpiling on 3
and 17 December 2024 were conducted for Contract 2;
•
Environmental toolbox trainings on protection and preservation of trees,
ground investigation, site clearance, formwork and falsework, fencing,
excavation, chemical waste and handling of chemical spillage, anti-mosquitos
control measures on 3, 5, 10, 12, 17, 19, 24 and 31 December 2024 were
conducted for Contract 3;
•
Environmental toolbox trainings on grouting, cement debagging and
mixing, milling, paving, plastering and paint on 4, 11, 18, 24 and 31 December
2024 were conducted for Contract 7.
The status of
statutory environmental compliance with the EP conditions under the EIAO,
submission status under the EP and implementation status of mitigation measures
are presented in Annex C.
The
environmental licenses and permits, including environmental permit, discharge
license under Water Pollution Control Ordinance, registration as chemical waste
producer, construction noise permit and specified processes license, which were
valid in the reporting period are presented in Annex D. No non-compliance with environmental
statutory requirements was recorded.
The temporary works area in Area 113 has been used by MTRC since
9 November 2024 under the Works Contract 1202 – Tung Chung East Station and
Associated Enabling Works for Track Diversions of Tung Chung Line Extension
(TUE) under the Environmental Permit (EP-614/2022). The corresponding
environmental monitoring, site inspection, environmental complaint handling and
EM&A reporting in the above-mentioned works area will be covered by
EM&A programme of TUE and carried out by existing
ET and IEC of TUE.
According to
the Updated EM&A Manual of the Project, impact air quality monitoring in
terms of 1-hour Total Suspended Particulate (TSP) was conducted three (3) times
every six (6) days when the highest dust impact was expected. The Action
and Limit Levels of the air quality monitoring is provided in Table 2.1
below.
Table 2.1 Action and Limit Levels for 1-hour TSP
Location |
Action Level (µg/m3) |
Limit Level (µg/m3) |
Monitoring station for Tung Chung East |
279 |
500 |
Portable direct reading dust meters were used
to measure 1-hour TSP levels in undertaking the air quality monitoring for the
Project. The proposed use of portable direct reading dust meters was
submitted to IEC and obtained agreement from the IEC as stated in Section 5.5
of the Updated EM&A Manual. With the use of direct reading dust
meter, it can allow prompt and direct results for the EM&A reporting and
the implementation of the event and action plan. The portable direct reading
dust meter would be calibrated every year against High Volume Sampler (HVS) to
check the validity and accuracy of the results measured by direct reading
method.
The monitoring
location and equipment used in the impact air quality monitoring programme are summarized in Table 2.2 and
illustrated in Figure 2.1.
Copies of the calibration certificates for the equipment are presented in Annex E1, which showed that
the portable direct reading dust meter is capable of providing comparable
results with that provided by a HVS.
Table 2.2 Air Quality Monitoring Details
Monitoring Station |
Location |
Parameter |
Frequency and Duration |
Monitoring Dates |
Equipment |
DM-1 |
Tung Chung Area 56 – Ying Tung Estate |
1-hour TSP |
Three times per six days during the construction period of the Project |
2, 7, 13, 19, 24 and 30 December 2024 |
1-hour TSP Dust Meter SIBATA LD-3B (S/N: 436560) |
Note: It
should be noted that impact monitoring at other construction dust monitoring
locations at TCE as stated in the Updated EM&A Manual will commence after
the flat intake (for Monitoring Stations DM-2, DM-3 and DM-4).
The schedule
for air quality monitoring during the reporting period is provided in Annex E2.
The monitoring
results for 1-hour TSP are summarized in Table 2.3. The monitoring
data and the graphical presentation are provided in Annex E3.
Table 2.3 Summary of 1-hour TSP Monitoring Results in the
Reporting Period
Monitoring Station |
Average (µg/m3) |
Range (µg/m3) |
Action Level (µg/m3) |
Limit Level (µg/m3) |
DM-1 |
43 |
34-49 |
279 |
500 |
Major dust sources in the reporting period
included haul road traffic and excavation under the Project.
No exceedance of
Action and Limit Levels was recorded for construction air quality monitoring in
the reporting period. No action was thus required to be undertaken in
accordance with the Event and Action Plan presented in Annex E4.
According to
the Updated EM&A Manual of the Project, impact noise monitoring was
conducted once per week during the construction phase of the Project. The
Action and Limit Level for construction noise of the Project is provided in Table
2.4 below.
Table 2.4 Action and Limit Levels for Construction Noise
Time Period |
Action Level |
Limit Level |
0700 - 1900 hours on normal weekdays |
When one documented complaint is received |
75 dB(A) a, b |
Note:
a
Limit level is exceeded when Leq ≥
75 dB(A). If works are to be carried out during restricted hours, the
conditions stipulated in the construction noise permit issued by the Noise
Control Authority have to be followed.
b Reduce to 70 dB (A) for schools and 65 dB (A) during school examination
periods.
Noise monitoring was performed using
sound level meter at the designated monitoring stations NMS-CA-1A ([3]) ([4])
and NMS-CA-4 (Figure 2.2; Table
2.5) in accordance with the requirements stipulated in the Updated EM&A Manual. Acoustic calibrator
was deployed to check the sound level meters at a known sound pressure
level. Details of the deployed equipment are provided in Table 2.5.
Copies of the calibration certificates for the equipment are presented in Annex F1.
Table 2.5 Noise
Monitoring Details
Monitoring Station a |
Location |
Parameter |
Frequency and Duration |
Monitoring Dates |
Equipment |
NMS-CA-1A b |
Residential premise in Tung Chung East – Century Link/Ying Hong Road c |
30-minute measurement between 0700 and 1900 on normal weekdays (Monday to Saturday). Leq, L10 and L90 would be recorded. |
Once per week for 30 mins during the construction period of the Project |
2, 7, 13, 19, 24 and 30 December 2024 |
Sound Level Meter: Rion NL-52 (S/N: 00331805)
Acoustic Calibrator: LARSON DAVIS CAL200 (S/N: 16172) |
NMS-CA-4 |
Residential premise in the reclamation area next to Tung Chung East – Ying Tung Estate |
Note:
a
It should be noted that impact monitoring at other construction
noise monitoring locations at TCE as stated in the Updated EM&A Manual will
commence after the flat intake of residential premise in TCE (for Monitoring
Station NMS-CA-1) and operation of schools (for Monitoring Stations NMS-CA-2
and NMS-CA-3).
b
Impact monitoring at monitoring station NMS-CA-1A commenced on 19
September 2018 in view of the close vicinity of the construction works near the
residential area at Century Link.
c
Due to land handover issue, NMS-CA-1A was relocated to Ying
Hong Road which is located 60m away from the original location. Proposal
on the relocation of NMS-CA-1A was approved by IEC on 23 November 2018.
Noise monitoring at the relocated location commenced since 24 November 2018.
The schedule
for noise monitoring during the reporting period is provided in Annex F2.
Results for
noise monitoring are summarized in Table 2.6. The monitoring data and
the graphical presentation are provided in Annex F3.
Table 2.6 Summary of
Construction Noise Monitoring Results in the Reporting Period
Monitoring Station |
Average, dB(A), |
Range, dB(A), Leq (30mins) |
Limit Level, dB(A), Leq (30mins) |
NMS-CA-1A |
67.0 |
66.4-67.9 |
75 |
NMS-CA-4 |
63.9 |
62.7-64.7 |
75 |
Major noise sources during the noise monitoring
included noise from plant operation, craning, piling, haul road traffic, nearby
traffic and aircraft as well as nearby construction sites.
No
Action/Limit Level exceedance was recorded for construction noise monitoring in
the reporting period. No action was thus required to be undertaken in
accordance with the Event and Action Plan presented in Annex F4.
No monitoring
event for impact water quality monitoring was conducted at all designated
monitoring stations during the reporting period. Water quality monitoring
has been suspended since 3 October 2023 as all reclamation works and marine
construction activities have been completed.
Compensation woodland planting
under Contract 2 was completed on 30 September 2022. With the approval
from EPD on the monitoring proposal in August 2023, quarterly
post-planting monitoring for compensation woodland was commenced in September
2023. Quarterly post-planting monitoring report was submitted
to EPD on 10 December 2024. Quarterly post-planting monitoring for the
compensation woodland was carried out on 14, 17, 19 and 30 December 2024.
Photographic record of the compensation woodland planting is provided in Annex G.
Plant species
of conservation importance, including three individuals of Aquilaria
sinensis and 33 individuals of Gmelina chinensis, were identified
within works areas for Contract 2 during the survey conducted in August
2021. All individuals of Aquilaria sinensis and 31 individuals of Gmelina
chinensis were recommended being preserved in-situ
while two individuals of Gmelina chinensis (RT-07 and RT-08) were
recommended being transplanted to the receptor site in accordance with the
Detailed Preservation and/or Translocation Plan for Plant Species of
Conservation Importance approved under Condition 2.21 of EP-519/2016.
Initial tree
survey was conducted in September 2021 under Contract No. NL/2020/02 before the
commencement of construction works. According to the initial tree survey
conducted, the in-situ preserved plant species of conservation
importance of which one individual of Aquilaria sinensis and six
individuals of Gmelina chinensis were found missing.
During the monthly monitoring of
the in-situ preserved plant species of conservation importance in
November 2023, one individual of Aquilaria sinensis and one individual
of Enkianthus quinqueflorus
were newly observed and recommended being preserved in-situ.
Registration and measurement for two additional trees were conducted on 4
December 2023.
Monthly
monitoring of the in-situ preserved plant species of conservation
importance by the Qualified Personnel (QP) appointed under Contract 2 was
implemented in the reporting period. Health condition was considered fair
for the majority of the in-situ preserved plant
species of conservation importance, of which two individuals of Gmelina
chinensis could not be monitored as a result of unsafe access to the
locations, as recorded during the monitoring carried out on 20 December
2024.
Tree protection
zones for the in-situ preserved plant species of conservation importance
were demarcated. No injuries and/or damages to the individuals of the in-situ
preserved plant species of conservation importance were reported by the QP
since the previous monitoring events. Photographic record and tree
schedule of the preserved plant species of conservation importance monitoring
are provided in Annex H1.
The ET will
continue to monitor the implementation of monitoring of in-situ
preserved plant species of conservation importance.
Site visit to
the receptor site for the transplanted plant species of conservation importance
under Contract 2 was carried out on 20 January 2022 prior to the commencement
of transplantation works for the transplanted plant species of conservation
importance on 21 January 2022.
The
transplanted plant species of conservation importance were both certified as
dead trees by the QP on 15 June 2022 as no living signs were observed.
Replacement planting of new trees of the same species, or other species to the
satisfaction of the Project Manager, at the Contractors’ expense would be
deemed necessary in accordance with the conditions under the approved Detailed
Preservation and/or Translocation Plan for Plant Species of Conservation
Importance. Replacement planting of three (3) Aquilaria sinensis
were completed on 28 April 2023. One (1) individual was certified dead by
the QP as no living signs were observed on 26 July 2023. The removal of
the dead tree and replanting of one (1) individual of Aquilaria sinensis
were completed on 19 September 2023.
The
establishment period of two (2) individuals of Aquilaria
sinensis was ended on 27 April 2024 and one (1) individual of Aquilaria
sinensis was ended on 18 September 2024.
Quarterly
monitoring of three (3) individuals of Aquilaria sinensis were carried
out on 19 December 2024. All three (3) individuals of
the replacement planting trees were in fair health condition.
Photographic record and tree schedule of Aquilaria sinensis monitoring
are provided in Annex H2.
The
transplanted plant species of conservation importance were watered twice a week
during the establishment period to keep the soil moist except in days with
heavy rainfall. The ET will continue to monitor the implementation of
monitoring of in-situ preserved/ transplanted plant species of conservation
importance.
The
construction of vertical eco-shoreline, mangrove eco-shoreline and rocky
eco-shoreline has been substantially completed. Photographic record is
provided in Annex I.
The 2nd Progress report
of the eco-shoreline monitoring was submitted to AFCD and EPD on 23 December
2024, summarizing the monitoring results with key findings of the wet season
monitoring conducted in May 2024 and August 2024.
No eco-shoreline monitoring was
scheduled during the reporting period. Monitoring is conducted for
at least 3 years after the completion of eco-shoreline, twice in wet season and
twice in dry season, while ichthyoplankton and juvenile fish monitoring will be
conducted on a monthly basis covering May to August
for at least 3 years, in order to determine the effectiveness of the
eco-shoreline in accordance with the Updated EM&A Manual and Eco-shoreline
Implementation Plan.
According to the Updated EM&A
Manual of the Project, post-construction soft shore ecological monitoring has
to be conducted quarterly at each survey location at Tung Chung Bay (TCB) and
Tai Ho Wan (THW) covering wet and dry seasons in the post-construction phase at
least for 2 year after completion of
construction. The soft shore ecological monitoring consisted of
qualitative walk-through surveys, quantitative transect surveys and
sedimentation rate monitoring at the accessible survey locations of TCB and THW.
For qualitative walk-through
surveys, the accessible shoreline of TCB and THW at each of the three shore
heights: 2 m, 1.5 m and 1 m above Chart Datum was surveyed, and organisms
encountered were recorded and their relative abundance noted. In particular, active search of horseshoe crabs and
seagrasses were conducted to confirm whether these species are present along
the sites.
For quantitative transect survey,
one 50 – 100 m horizontal (belt) transect (actual length subject to the site
conditions) was surveyed at each of the three shore heights: 2 m, 1.5 m and 1 m
above Chart Datum of each survey location. On each transect, five
quadrats (50 cm x 50 cm) were placed randomly in each transect to assess the
abundance and distribution of flora and fauna. For each quadrat, surface
layer to 5 cm depth was sieved and microbenthic organisms (e.g. crustaceans)
were recorded and identified. Density of organisms was expressed as
individuals / m2. Areas with seagrass were also recorded and
identified and other information, such as the percentage cover, were also
recorded. Sessile animals such as barnacles and oysters in each quadrat
were not counted but estimated as percentage cover on the rock surface.
All species of algae (encrusting, foliose and filamentous) were also identified
and recorded by estimating the percentage cover on the rock surface. All
organisms were identified to the lowest possible taxonomic level (at least Genus level). Species encountered outside the quadrat
but in the vicinity of survey transect were also recorded.
For sedimentation rate monitoring,
to avoid disturbance to the mudflat and nuisance to navigation, no fixed
marker/monitoring rod was installed at the monitoring stations. A high precision
Global Navigation Satellite System (GNSS) real time location fixing system was
used to locate the station in the precision of 1 mm, which is reasonable under
flat mudflat topography with uneven mudflat surface only at micro
level.
Measurements were taken directly on
the mudflat surface. The Real Time Kinematic GNSS (RTK GNSS) surveying
technology was used to measure mudflat surface levels and 3D coordinates of a
survey point. The RTK GNSS survey was calibrated against a reference
station in the field before and after each survey. The reference station
is a survey control point established by the Lands Department of the HKSAR
Government using professional surveying instruments such as total station,
level and geodetic global navigation satellite system. The coordinates
system is in HK1980 GRID system. The reference station was surveyed and
established by traditional land surveying methods using professional surveying
instruments such as total station, level and geodetic GNSS. The accuracy
was down to mm level and higher than the proposed RTK GNSS cm level so that the
reference control station has relatively higher accuracy. As the
reference control station has higher accuracy, it was set as true evaluation
relative to the RTK GNSS measurement. All position and height correction
were adjusted and corrected to the reference control station.
The precision of the measured
mudflat surface level reading (vertical precision setting) was within 10 mm
(standard deviation) after averaging the valid survey records of the XYZ HK1980
GRID coordinates. Each survey record at each station was computed by
averaging at least three measurements that are within the above specified
precision setting. Both digital data logging and written records were
collected in the field. Field data on station fixing and mudflat surface
measurement were recorded.
The schedule for soft shore
ecological monitoring during the reporting period is provided in Annex J1.
Post-construction soft shore
ecological monitoring was conducted at three (3) monitoring locations at Tung
Chung Bay (TCB), situated in the eastern side (TCB1), southern side (TCB2) and
western side (TCB3) as well as one (1) monitoring location at Tai Ho Wan (THW)
as shown in Figure 2.3
during the reporting period. Representative photographs taken during the
impact monitoring are presented in Figure 2.4.
For qualitative
walk-through surveys, horseshoe crabs and intertidal soft shore communities
were recorded during the post-construction monitoring. The survey results
for each monitoring location are summarized in Table 2.7 below and
detailed in Annex J2.
Table 2.7 Summary of Qualitative Walk-through Surveys
Location |
Date and Time a |
Horseshoe Crabs |
Seagrass |
No. of Other Intertidal Species |
||
No. of Species |
No. of Individuals |
No. of Species |
Area Coverage (m2) |
|||
TCB3 |
05/12/2024 08:30-12:30 |
1 |
2 |
- |
- |
30 |
TCB1 |
09/12/2024 09:30-12:30 |
1 |
1 |
- |
- |
30 |
TCB2 |
18/12/2024 08:30-12:30 |
0 |
0 |
- |
- |
27 |
THW |
19/12/2024 09:30-13:30 |
1 |
4 |
- |
- |
32 |
Note:
a
Quantitative and qualitative transect surveys were conducted on 5 December 2024
at TCB3, 9 December 2024 at TCB1, 18 December 2024 at TCB2, and 19 December
2024 at THW.
For the quantitative
transect surveys, a total of 12,794 individuals were recorded from all
transects at monitoring stations TCB1, TCB2, TCB3 and THW. The most
abundant group of intertidal soft shore communities recorded was gastropods,
with a total of 12,665 individuals (relative abundance of 99.0% and density of
844.3 individual m-2). The summary of the top three dominant
species at each shore height of each monitoring station and the complete list
of species and density recorded are presented in Annex J2. When compared with the results
obtained during the baseline monitoring as presented in the Baseline Monitoring
Report [5], there was no indication of a change in
the composition of intertidal communities recorded during the reporting period.
The mudflat
surface levels at the four selected monitoring stations in December 2024 and
the corresponding XYZ HK1980 GRID coordinates are presented in Table 2.8.
When compared with the results obtained during the baseline monitoring as
presented in the Baseline Monitoring Report, slight changes with <0.07 mPD of sediment levels are recorded for the monitoring
stations. The ET will continue to observe the trend of change in sediment
levels over time for further comparison and review.
Table 2.8 Results of Sedimentation Rate Monitoring
Monitoring Station |
Northing (m) |
Easting (m) |
Z level at December 2024 (mPD) |
Remarks |
TCB1 |
816068.628 |
811129.275 |
1.287 |
Soft mudflat |
TCB2 |
815812.688 |
810917.378 |
1.010 |
Soft mudflat |
TCB3 |
816027.454 |
810696.215 |
0.977 |
Soft mudflat |
THW |
817472.071 |
815850.375 |
1.000 |
Soft mudflat |
Based on the post-construction monitoring
results, there was no evidence showing any significant difference in intertidal
communities when compared against the data obtained during baseline
monitoring. No action is thus required to be undertaken in accordance
with the Event and Action Plan presented in Annex J3. The ET will continue to observe the
change in density or the distribution pattern of horseshoe crab, seagrass and
intertidal soft shore communities taking into account
natural fluctuation in respect of the occurrence and distribution pattern.
Site inspections
were carried out on a weekly basis with the Contractor and ER to monitor the
implementation of proper environmental pollution control and mitigation
measures for air quality, noise, water quality, waste management, marine
ecology, landscape and visual impacts and preservation and/or transplantation
of plant species of conservation importance under the Project. In the
reporting period, five (5) site inspections were carried out on 4, 11, 18, 24
and 31 December 2024 for Contract 2, four (4) site inspections were carried out
on 5, 13, 17 and 27 December 2024 for Contract 3 and five (5) site inspections
were carried out on 3, 10, 17, 24 and 31 December 2024 for Contract 7.
Key
observations during the site inspections are summarized in Table 2.9.
Table 2.9 Key Observations Identified during the Site
Inspection in this Reporting Month
Contract No. |
Inspection Date |
Environmental Observations |
Recommendations/ Remarks |
Contract 2 |
4 December 2024 |
Portion 3, TTA • No deficiency was observed. |
• Nil.
|
11 December 2024 |
Portion 3, TTA • No deficiency was observed. |
• Nil.
|
|
18 December 2024 |
Portion 3 • Chemical containers were observed placing on the ground.
Portion 6 • Poor housekeeping was observed. |
Portion 3 • Contractor was reminded to provide drip tray for chemicals.
Portion 6 • The Contractor was reminded to maintain good housekeeping. |
|
24 December 2024 |
Portion 3 • Oil stain was observed on ground. |
Portion 3 • The Contractor was urged to clean the oil stain and rectify the situation immediately. |
|
31 December 2024 |
Portion 3 • Drainage blockage was observed. |
Portion 3 • The Contractor was reminded to remove the waste and keep the drainage system clean. |
|
Contract 3 |
5 December 2024 |
Portion 10, TTA • No deficiency was observed. |
• Nil. |
13 December 2024 |
Portion 16b • Poor drainge system was observed. |
Portion 16b • The Contractor was urged to rectifiy immediately and ensure wastewater would be properly treated before discharge. |
|
17 December 2024 |
Portion 10 • Proper and outstanding record was not observed on the wastewater treatment system tank checklist.
TTA • Oil stain was observed. |
Portion 10 • The Contractor was reminded to provide proper checking and record on the wastewater treatment system tank checklist.
TTA • The Contractor was urged to clean the oil stain and rectify the situation immediately. |
|
Portion 16b • General refuse was observed on ground. |
Portion 16b • The Contractor was reminded to maintain good housekeeping. |
||
Contract 7 |
3 December 2024 |
Portion 31 • Chemical containers were observed placing on the ground. |
Portion 31 • The Contractor was reminded to place the chemical containers in drip tray. |
10 December 2024 |
Portion 31 • No deficiency was observed. |
• Nil. |
|
17 December 2024 |
Portion 146 • Chemical container was observed placing on the ground. |
Portion 146 • The Contractor was reminded to place the chemical container in drip tray. |
|
24 December 2024 |
Portion 31 • No deficiency was observed. |
• Nil. |
|
31 December 2024 |
Portion 146 • Appropriate Non-road Mobile Machinery (NRMM) label was not observed on generator. |
Portion 146 • The Contractor was reminded to affix appropriate NRMM labels in accordance with the Air Pollution Control (Non-road Mobile Machinery) (Emission) Regulation. |
The Contractors
have rectified all of the observations identified
during environmental site inspections in the reporting period. The Contractors were reminded to implement all
relevant mitigation measures related to construction dust, construction noise,
water quality and waste management outlined in the EIA Report and Updated
EM&A Manual.
The Contractors of Contract 1, 2, 3
and 7 have registered as chemical waste producer. Sufficient
numbers of receptacles were available for general refuse collection and
sorting.
All dump trucks engaged on site was
equipped with RTTM system during the reporting period. The Surveillance
Team of the ET conducted regular site inspection on the dump trucks and their
track records. No illegal dumping and landfilling of C&D materials
was found during the reporting period.
Wastes generated during this
reporting period include mainly non-inert construction wastes. Reference
has been made to the waste flow tables prepared by the Contractors. The
quantities of different types of wastes and imported fill materials are summarised in Table 2.10.
Table 2.10
Quantities of Different Waste Generated and Imported Fill Materials
Contract No. |
Month/Year |
Inert C&D Materials a (m3) |
Imported Fill b (sand) (m3) |
Imported Fill c (public fill) (m3) |
Inert Construction Waste Re-used d (m3) |
Non-inert Construction Waste e (m3) |
Recyclable Materials f (kg) |
Chemical Wastes (kg) |
TCNTE (East) |
1 to 31 Oct 24 |
0.0 |
0.0 |
0.0 |
17,042.0 |
295.0 |
364.0 |
1,600.0 |
1 to 30 Nov 24 |
2,085.0 |
0.0 |
0.0 |
9,271.0 |
244.69 |
0.0 |
0.0 |
|
1 to 31 Dec 24 |
0.0 |
0.0 |
0.0 |
154,609.0 |
266.1 |
0.0 |
0.0 |
Note:
a Inert construction wastes include hard
rock and large broken concrete, and materials disposed as public fill.
b Imported
materials include of sand fill from any source outside of TCNTE.
c
Imported sorted public fill include all G200, G400 and glass gullet (local
recycling materials) from any source outside of TCNTE.
d
Reuse of inert construction waste generated under the TCNTE contracts.
e Non-inert construction wastes include general refuse
disposed at landfill.
f
Recyclable materials include metals, paper, cardboard, plastics
and others.
Implementation of applicable
landscape and visual mitigation measures was monitored in accordance with the
Updated EM&A Manual. All measures undertaken by the Contractor during
the construction phase and establishment work phase shall be audited by ET to
ensure compliance with the intended aims of the measures.
The implementation status of the
environmental protection measures is summarized below in Table 2.11.
Examples of landscape and visual mitigation measures are presented in Annex K1. The
monitoring programme for detailed design,
construction and establishment stages is presented in Table 2.12.
Event and Action Plan for Landscape and Visual impacts is stated in Annex K2.
Table 2.11
Implementation Status of Landscape and Visual Mitigation Measures
Landscape and Visual Mitigation Measures during Construction |
Implementation Status |
Relevant Contract(s) in the Reporting Period |
MM1 – Optimization of Construction Areas & Providing Temporary Landscape on Temporary Construction |
Implementation of the measures were carried out during the detailed design stage of the Project. |
NA
|
MM2 – Minimize Topographical Changes |
Implementation of the measures were carried out during the detailed design stage of the Project. |
NA |
MM3 – Preservation of Potentially Registerable OVTs, Rare and Protective Vegetation |
Tree Protection Specifications were provided in the relevant Contract Specifications respectively for implementation by the Contractors under the Project. The Contractors submitted Detailed Preservation and/or Translocation Plan for Plant Species of Conservation Importance under EP condition 2.21. The Contractors’ performance on the implementation of the tree maintenance and protection measures were observed and checked by the ET weekly during construction period. |
All works contracts |
MM4 – Transplanting of Existing Trees
|
Tree Transplanting Specifications were provided in the relevant Contract Specifications respectively for implementation by the Contractors under the Project where trees would unavoidably be affected by the construction works. The Contractors submitted Detailed Preservation and/or Translocation Plan for Plant Species of Conservation Importance under EP condition 2.21. The transplanted plant species of conservation importance were both certified as dead trees by the QP on 15 June 2022 as no living signs were observed. |
Contract 2 |
MM5 – Screen Hoarding
|
All works contracts |
|
MM6 – Adopting Non-dredge Method for the Reclamation |
Not applicable during the reporting period. |
NA |
MM9 – Providing Natural Rock Material/ Planting for Artificial Seawall |
Rock armour reused and construction of eco-shoreline (mangrove eco-shoreline, rocky eco-shoreline and vertical eco-shoreline) in progress. The implementation of mitigation measures was checked by ET during weekly site inspection. Implementation of the measures by Contractors was observed. |
Contract 1 |
MM10 – Compensatory Planting |
Not applicable during the reporting period. |
NA |
MM11 – Woodland Restoration |
The implementation of mitigation measures was checked by ET during weekly site inspection. Implementation of the measures by Contractors was observed. |
Contract 2 |
MM12 – Screen Planting |
Not applicable during the reporting period. |
NA |
MM13 – Roadside Planting |
Not applicable during the reporting period. |
NA |
MM14 – Aesthetic Design of Built Development |
Not applicable during the reporting period. |
NA |
MM15 – Maximise Greening on Structures |
Not applicable during the reporting period. |
NA |
MM16 – Noise Barrier Design |
Not applicable during the reporting period. |
NA |
MM18 – Landscaping on Slopes |
Not applicable during the reporting period. |
NA |
MM20 – Lighting Control |
The implementation of mitigation measures was checked by ET during weekly site inspection. Implementation of the measures by Contractors was observed. |
All works contracts |
Table 2.12 Monitoring Programme for
Landscape and Visual
Stage |
Monitoring Task |
Monitoring Report |
Form of Approval |
Frequency |
Design |
Monitoring of design works against the recommendations of the landscape and visual impact assessments within the EIA should be undertaken by the Engineer and Landscape Architect, to ensure that they fulfil the intentions of the mitigation measures. Any changes to the design, including design changes on site should also be checked |
Report by CEDD / ER confirming that the design conforms to requirements of EP. |
Approval by Project Proponent |
At completion of design stage |
Construction |
Monitoring of the contractor’s operations during the construction period. |
Report on Contractor's compliance by ET |
Counter-signature of report by IEC |
Monthly |
Establishment Works |
Monitoring of the planting works during the 24-months Establishment Period after completion of the construction works. |
Report on Contractor's compliance by ET |
Counter-signature of report by IEC |
Bi-monthly |
A summary of the
Environmental Mitigation Implementation Schedule is presented in Annex B. The necessary
mitigation measures were implemented properly for the Project.
There was no
notification of summons or prosecution recorded in the reporting period.
No environmental complaint was received in the
reporting period.
Statistics on complaints, notifications of
summons, successful prosecutions are summarised in Annex L.
Works to be undertaken in the
next monitoring period of January 2025 are summarized in Table 3.1
below, together with the key issues and the key mitigation measures:
Table 3.1 Major Activities for the
Next Reporting Period
Activities |
Key Issues |
Key Mitigation Measures |
Contract No. NL/2017/03 - Tung Chung New Town Extension – Reclamation and Advance Works (Contract 1) |
||
Land-based Works |
||
• Removal of siltation at IORC
|
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management · Potential surface runoff · Noise from plant operation during normal working hours or restricted hours · Dust emission during storage and transfer of sand/ sorted public fill |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management · Strictly follow requirement under CNP for the use of PMEs and works within restricted period · Use of acoustic mat and other noise mitigation measures when necessary · Regular maintenance of engines and mechanical equipment |
Contract No. NL/2020/02 - Tung Chung New Town Extension – Salt Water Supply System (Contract 2) |
||
Land-based Works |
||
· Construction of pumping station at Portion 6 · Construction of Intake Culvert at Portion 6 · Construction of service reservoir and TMF mainlaying at Portion 3 · Construction of HDD works at Portion 3 · Watermain laying works at Portion 3 along Man Tung Road, Coastal Skyline and Waterfront Road · Construction of L3 Road at Portion 5
|
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management · Tree protection |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management · Retain and protect all existing trees and vegetation within the study area which are not directly affected by the works |
Contract No. NL/2020/03 - Tung Chung New Town Extension – Major Infrastructure Works in Tung Chung East (Contract 3) |
||
Land-based Works |
||
· Excavation and ELS works at Portion 104 · Excavation and ELS works at CUT no.1, 2, 3, 4 and supporting building · Construction works for CUT no. 1 and 3 structure · UU laying works in CUT 1 · Back-filling works for CUT 2 · Construction works and furniture installation of PM office at WA9 · Construction works of Contractor office at WA6 · Drainage, Sewerage and watermain works at Road L5, L7, L8, L9, D4 and D5 and Portion 16 · DCS works at Road L5, D4 and L7. · Pipe laying works for twin rising mains/ watermain laying at Man Tung Road · Preparation and pipe jacking works at Ying Tung Road · Pipe jacking works at Yi Tung Road · Backfilling works for noise barrier at Portion 11 · Road and drainage works in Road P1 · Road works in Road L3, L4 and L5 · Road widening works at Ying Hei Road · ELS for SIBC construction · Construction for BC3 at Portion 22B · Pipe pile installation at underpass D1
|
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management |
Contract No. NL/2020/07 - Tung Chung New Town Extension – Tai Ho Interchange (Contract 7) |
||
Land-based Works |
||
· Open cut excavation, backfilling and pipe laying for rising main and watermain at Portion 146-1 to 146-5 · Pak Mong Bridge insitu construction of abutment, diaphragm and cable trough · Trench excavation and pipe laying works at Portions 32 (Sham Shui Kok Drive) · Trench excavation and pipe laying works at Portion 32 (Access Road adjacent to MTRC Siu Ho Wan Depot) · Establishment of pipe jacking works at Portion 33 · Horizontal grouting at Receiving pit at Portion 32 · RC construction of Retaining Wall FR1 at Portion 31 · Pak Mong Subway Extension Phase 2 - Demolition of existing Subway and Sheetpiling for ELS · Formwork and rebar fixing for Bridge A1 and A2 · RC construction for A1a, A1b, A2a, A2b Abutment · RC construction at RW-R7 at Portion 31 · RC works at Wall E · Mini-piles at Wall D · Pile cap construction for Bridge C at Portion 146-12 · Excavation and RC works for Box Structure C1 at Portion 146-11 · Pipe connection to BC6 from Portion 147 · U channel and chain link fence construction at Portion 147-1 and 147-2 · Earthworks at SR-A3 near RW-R7 · Drainages works at SR-A2, A3 and A5 · Drainages works at 146-4, 146-6 and 146-7 · Site clearance and tidiness |
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management · Tree protection |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management · Retain and protect all existing trees and vegetation within the study area which are not directly affected by the works |
The ET will keep track on the construction
works to confirm compliance of environmental requirements and the proper
implementation of all necessary mitigation measures. The ET will also
recommend to the Contractors about the environmental toolbox topics on the
abovementioned key issues for the next reporting period.
The tentative schedules for
environmental monitoring in January 2025 are provided in Annex M.
This
EM&A Report presents the findings of the EM&A activities undertaken for
the TCE Project during the period from 1 to 31 December 2024 in accordance with
the Updated EM&A Manual and the requirements of the Environmental Permit
(EP-519/2016). The environmental monitoring, site inspection,
environmental complaint handling and EM&A reporting in the temporary works
area in Area 113 used by MTRC will be covered by EM&A programme
of TUE and carried out by existing ET and IEC of TUE.
Air
quality (1-hour TSP), noise, compensation woodland, in-situ preserved plant species
of conservation importance, transplanted plant species of conservation
importance and post-construction soft shore ecological monitoring were carried
out in the reporting period.
The
monitoring results for air quality monitoring (1-hour TSP) complied with the
Action/ Limit levels in the reporting period.
No
exceedance of Action/Limit Level was recorded for construction noise monitoring
in the reporting period.
Water
quality monitoring was suspended in the reporting period.
Mangrove
eco-shoreline, rocky eco-shoreline and vertical eco-shoreline were
completed. No eco-shoreline monitoring was scheduled during the reporting
period.
Based on
the monitoring results for post-construction soft shore ecological monitoring,
there was no evidence showing any significant change in intertidal communities
when compared against the data obtained during baseline monitoring. The
ET will continue to observe the change in density or the distribution pattern
of horseshoe crab, seagrass and intertidal soft shore communities taking into account natural fluctuation in respect of the
occurrence and distribution pattern.
Post-planting
monitoring of the compensation woodland was carried out in the reporting month.
Monitoring
of the in-situ preserved plant species of conservation importance and
monitoring of the transplanted plant species of conservation importance were
carried out in the reporting period.
Environmental
site inspections were carried out during the reporting period.
Recommendations on remedial actions were given to the Contractors for the
deficiencies identified during the site inspections.
There
were no notification of summons or prosecution recorded in the reporting
period. No environmental complain was received in the reporting period.
The ET
will keep track on the construction works to confirm compliance of
environmental requirements and the proper implementation of all necessary
mitigation measures.
([1])
ERM (2018a). Updated Environmental Monitoring and Audit Manual for
Tung Chung New Town Extension. Deposited to EPD under EP-519/2016
([2])
Arup (2015). Environmental Impact Assessment Report for Tung Chung
New Town Extension. Deposited to EPD under Register No. AEIAR-196/2016
([3])
Impact monitoring at monitoring station NMS-CA-1A commenced on 19
September 2018 in view of the close vicinity of the construction works near the
residential area at Century Link.